Construction on 550 MW Topaz Solar Farm underway

Share

Despite fears the project wouldn’t get off the ground after the thin film manufacturer failed to secure a U.S. Department of Energy loan, and due to permitting delays, work finally got underway last week, meaning that it can now qualify for the 30 percent tax grant program, which is expiring at the end of 2011.

As Jefferies points out in a company note issued, the move is a "modest positive" as it "signals all regulatory hurdles have been cleared".

Overall, the Topaz project is expected to be built over a period of around three years. Currently, First Solar is using its own balance sheet to fund the project, however it is looking for a buyer. Jeffries further notes, "No project sale will be recognized until the project is sold, but it can book revenue per its PPA with PG&E (PCG, $37.21, Hold) as the project comes online and produces electricity. Modules going into the project are accounted as inventory until the project is sold."

The power purchase agreement has been in place since August 2008, four months after the project was first proposed by OptiSolar. It is estimated that the project will cost around $1 billion to execute.

First Solar has already completed a number of large-scale solar projects, including the 48 MW Copper Mountain system, the 30 MW Cimarron system and, currently the world's largest, the 80 MW Sarnia system in Ontario.

Popular content

This content is protected by copyright and may not be reused. If you want to cooperate with us and would like to reuse some of our content, please contact: editors@pv-magazine.com.

Share

Related content

Elsewhere on pv magazine...

Leave a Reply

Please be mindful of our community standards.

Your email address will not be published. Required fields are marked *

By submitting this form you agree to pv magazine using your data for the purposes of publishing your comment.

Your personal data will only be disclosed or otherwise transmitted to third parties for the purposes of spam filtering or if this is necessary for technical maintenance of the website. Any other transfer to third parties will not take place unless this is justified on the basis of applicable data protection regulations or if pv magazine is legally obliged to do so.

You may revoke this consent at any time with effect for the future, in which case your personal data will be deleted immediately. Otherwise, your data will be deleted if pv magazine has processed your request or the purpose of data storage is fulfilled.

Further information on data privacy can be found in our Data Protection Policy.