Germany: Parabel to develop 90 MW PV park

Share

Following final approval, which should be concluded in May, the Berlin company will erect the system on the site of a former military training ground.

The first phase of construction is scheduled to run from this June to August, and is expected to generate 41 MW. To achieve this, a spokesperson for the company tells pv magazine that around €90 million will be invested.

They continue by saying that the full 90 MW is expected to be reached by 2012. Additionally, it is hoped that up to 200 workers will be employed during the park's installation.

According to Parabel, Marienfliess municipality, which is responsible for land-use planning in the area, is very positive about the venture and has reportedly offered the process its full support.

"Using conversion areas for photovoltaic facilities is a sensible and attractive option from both an ecological and an economic point of view," says Jürgen Will, managing director of Parabel AG. "We are currently conducting an investor selection process and we invite all investors with an interest in the project to contact us by the end of February."

Last year, the company installed four open-field solar parks in Germany and the Czech Republic with a capacity of over 19 MWp.

Popular content

This content is protected by copyright and may not be reused. If you want to cooperate with us and would like to reuse some of our content, please contact: editors@pv-magazine.com.

Share

Related content

Elsewhere on pv magazine...

Leave a Reply

Please be mindful of our community standards.

Your email address will not be published. Required fields are marked *

By submitting this form you agree to pv magazine using your data for the purposes of publishing your comment.

Your personal data will only be disclosed or otherwise transmitted to third parties for the purposes of spam filtering or if this is necessary for technical maintenance of the website. Any other transfer to third parties will not take place unless this is justified on the basis of applicable data protection regulations or if pv magazine is legally obliged to do so.

You may revoke this consent at any time with effect for the future, in which case your personal data will be deleted immediately. Otherwise, your data will be deleted if pv magazine has processed your request or the purpose of data storage is fulfilled.

Further information on data privacy can be found in our Data Protection Policy.