The project, installed atop the Weidenhammer Packaging Group’s newly constructed manufacturing building, was both initiated and led by Athos Solar.

It is comprised of 2,021 Yingli photovoltaic modules, and utilizes the Goldbeck developed substructure.

A spokesperson told pv magazine that the system took around 20 days to install, and occurred concurrently with construction of Weidenhammer's building.

"For obvious reasons," he explianed, "the construction tasks were phased to align with progress of the building itself. For example, we installed the brackets, waited for the rooftop to be complete, then began with panel installation."

Popular content

This content is protected by copyright and may not be reused. If you want to cooperate with us and would like to reuse some of our content, please contact: editors@pv-magazine.com.

Share

Related content

Elsewhere on pv magazine...

Leave a Reply

Please be mindful of our community standards.

Your email address will not be published. Required fields are marked *

By submitting this form you agree to pv magazine using your data for the purposes of publishing your comment.

Your personal data will only be disclosed or otherwise transmitted to third parties for the purposes of spam filtering or if this is necessary for technical maintenance of the website. Any other transfer to third parties will not take place unless this is justified on the basis of applicable data protection regulations or if pv magazine is legally obliged to do so.

You may revoke this consent at any time with effect for the future, in which case your personal data will be deleted immediately. Otherwise, your data will be deleted if pv magazine has processed your request or the purpose of data storage is fulfilled.

Further information on data privacy can be found in our Data Protection Policy.