Designed to streamline permitting processes, BLM's Western Solar Plan approved the three PV projects in under 10 months.

Via a competitive auction, held last June by BLM, US$5.8 million was raised for solar leasing on six parcels of public land in the Dry Lake Solar Energy Zone (SEZ) in County Clark, Nevada.

The projects include Invenergy Solar Development LLC’s Harry Allen Solar Energy Center, which is expected to be up to 134 MW in size. Following the approval, Invenergy has applied for a right of way (ROW) grant to construct, operate, maintain, and decommission the ground-mounted project across two phases totaling 112 MW and 18 MW, respectively.

First Solar’s 200 MW Playa Solar Project also received approval and is now seeking a ROW grant. It is set to be built around 14 miles northeast of the city of Las Vegas. NV Energy’s around 100 MW Dry Lake Solar Energy Center was the final project to be given the green light by BLM.

Commenting, U.S. Secretary of the Interior Sally Jewell said, "Through thoughtful planning and upfront public participation, these solar projects demonstrate we can reduce permitting times, create certainty for energy developers, and achieve better outcomes for communities and the environment."

Popular content

This content is protected by copyright and may not be reused. If you want to cooperate with us and would like to reuse some of our content, please contact: editors@pv-magazine.com.

Share

Related content

Elsewhere on pv magazine...

Leave a Reply

Please be mindful of our community standards.

Your email address will not be published. Required fields are marked *

By submitting this form you agree to pv magazine using your data for the purposes of publishing your comment.

Your personal data will only be disclosed or otherwise transmitted to third parties for the purposes of spam filtering or if this is necessary for technical maintenance of the website. Any other transfer to third parties will not take place unless this is justified on the basis of applicable data protection regulations or if pv magazine is legally obliged to do so.

You may revoke this consent at any time with effect for the future, in which case your personal data will be deleted immediately. Otherwise, your data will be deleted if pv magazine has processed your request or the purpose of data storage is fulfilled.

Further information on data privacy can be found in our Data Protection Policy.