Work on 123 MW Italian PV project underway

Share

Construction on the first 39 MW phase is scheduled for completion next March, Currently, the foundations are being laid, module plates assembled, and medium voltage line to the feed-in point and transformer station built. In January, the company believes the photovoltaic modules and inverters will be added.

Construction on the remaining 84 MW is then expected to take place in the second quarter of 2012. It is hoped that the entire 123 MW will be grid connected by the end of the year.

JA Solar is supplying the modules needed for the project, SMA the inverters, and Hilti the mounting systems. Meanwhile, Conecon is working on some assembly parts, as is Biosar, and Siemens is building the transformer station. Finally, Enerparc is undertaking the DC planning, while BFP takes on the AC planning.

While solarhybrid and the component manufacturers are acting as interim investors, the project is expected to be marketed to other investors once it has been grid connected. "…the plant will be sold to the end investor and the financing by a bank will take place," explained the German solar company in a statement. This is the first time solarhybrid has tried this strategy. "For this purpose flawless documentation in the form of various positive due diligence reports is required," it added.

In 2011, solarhybrid says it installed solar power plants worth 218 MWp. Looking ahead to next year, it expects to install a further 200 MW of projects in Germany. It adds that photovoltaic projects in Bulgaria, South Africa, Israel and the U.S. are lined up.

Popular content

This content is protected by copyright and may not be reused. If you want to cooperate with us and would like to reuse some of our content, please contact: editors@pv-magazine.com.

Share

Related content

Elsewhere on pv magazine...

Leave a Reply

Please be mindful of our community standards.

Your email address will not be published. Required fields are marked *

By submitting this form you agree to pv magazine using your data for the purposes of publishing your comment.

Your personal data will only be disclosed or otherwise transmitted to third parties for the purposes of spam filtering or if this is necessary for technical maintenance of the website. Any other transfer to third parties will not take place unless this is justified on the basis of applicable data protection regulations or if pv magazine is legally obliged to do so.

You may revoke this consent at any time with effect for the future, in which case your personal data will be deleted immediately. Otherwise, your data will be deleted if pv magazine has processed your request or the purpose of data storage is fulfilled.

Further information on data privacy can be found in our Data Protection Policy.