Germany installs 775 MW of PV in Q1 2013

Share

According to Germany’s Federal Environment Minister, Peter Altmaier, new photovoltaic systems totaling 290 MW were added in March. If this figure is confirmed by the Federal Network Agency – expected no earlier than the end of April –then a total of 775 MW of photovoltaics were installed in Q1 2013.

After the agency confirms the installation figures, it must then publish the solar subsidy degression for May. This will be calculated based on the amount of photovoltaics installed between July 2012 and March 2013. According to the latest figures from Altmaier, installs total 3.98 GW. This is then extrapolated to an annual installation figure – which would be around 5.3 GW of newly installed photovoltaic capacity.

If this proves correct, the government mandated photovoltaic construction limit of 2.5 to 3.5 GW would be exceeded by more than 1.8 GW. As such, feed-in tariffs would fall by a further 1.8% in May, to between €0.1082 to €0.1563/kWh, depending on system size.

If more is installed in March than 290 MW, then solar subsidies would fall by 2.2% in May.

Translated by Becky Beetz.

Popular content

This content is protected by copyright and may not be reused. If you want to cooperate with us and would like to reuse some of our content, please contact: editors@pv-magazine.com.

Share

Related content

Elsewhere on pv magazine...

Leave a Reply

Please be mindful of our community standards.

Your email address will not be published. Required fields are marked *

By submitting this form you agree to pv magazine using your data for the purposes of publishing your comment.

Your personal data will only be disclosed or otherwise transmitted to third parties for the purposes of spam filtering or if this is necessary for technical maintenance of the website. Any other transfer to third parties will not take place unless this is justified on the basis of applicable data protection regulations or if pv magazine is legally obliged to do so.

You may revoke this consent at any time with effect for the future, in which case your personal data will be deleted immediately. Otherwise, your data will be deleted if pv magazine has processed your request or the purpose of data storage is fulfilled.

Further information on data privacy can be found in our Data Protection Policy.