Interest increases in Brazilian solar market, but challenges remain

Share

Empresa de Pesquisa Energetica, or EPE, the research arm of the Ministry of Mines and Energy in Brazil, has recently released a 60 page report, in Portuguese, on the solar industry, designed to aid in the creation of a specific solar policy in the country.

According to ANEEL, Brazil’s national electricity regulatory agency, which summarized the report in English, distributed rooftop solar power generation is already competitive with traditional electricity sources in some areas of the country, with these costs less than those sold by 10 of the 63 electricity distributors in Brazil. While centralized power generation is said to still be more expensive than other energy sources, falling photovoltaic costs are expected to help its integration.

"Following the introduction of ANEEL’s net metering legislation in April of this year, a boom is expected in the commercial and industrial rooftop PV market as businesses look to reduce their energy costs," stated the agency.

In order to build a strong solar energy industry, EPE is reported to have said that further incentives are required. One of its suggestions is the introduction of a specific solar auction "that would send a clear message of Brazil’s commitment to solar power."

ANEEL, reporting on EPE’s findings, says that around 20 MW of photovoltaics has already been installed in Brazil. The majority of this is said to be located in remote, off-grid systems. Furthermore, the agency says it has selected 17 projects, worth 23.6 MW to "evaluate the technical and commercial arrangements required to integrate solar projects into the grid". They are scheduled to be online in the next three years.

Skeptical

While ANEEL is confident of solar’s future in Brazil, the International Energy Agency, in its recently released renewable energy, medium-term market report 2012, has said that while renewable energy development is expected to grow in the country, photovoltaics will play a relatively small role.

Overall, it expects to see wind and hydro power resources grow "significantly" in Brazil, with an estimated capacity of eight GW and 21 GW to be added, respectively, by 2017, thus taking cumulative installed renewable energy capacity from 98 GW in 2011, to 128 GW in 2017. Meanwhile, the IEA says photovoltaic development is predicted to "proceed more slowly", due to the higher costs involved. Overall, it forecasts the addition of just 900 MW of photovoltaics by 2017.

It writes, "Outside of rural electrification efforts, solar PV has remained largely absent from renewable energy development, partly due to the government’s skepticism on its economic viability compared with other sources. Indeed, the PDE, thus far, has not factored this technology into its capacity projections."

Despite this, it does recognize that efforts are underway to introduce new solar policies, including the aforementioned auction, tax reductions and transmission incentives for solar energy under the proposed Prosolar program. It adds that ANEEL’s new net metering rules should stimulate photovoltaic development.

In terms of financing, the IEA believes Brazil is invested in renewable energy. "The country’s power sector, in general, has attracted a significant capital influx in recent years with the auction system providing an attractive entry mechanism. Moreover, the state-backed Brazilian Development Bank (BNDES) plays a large role in renewable energy investments by offering low-interest loans to a significant number of projects," it says.

Overall, it adds that the main challenges to implementation are:

  • Cost reductions through auctions, which may increase project vulnerability and head-to-head competition, which may price out some technologies;
  • A lack of streamlined environmental licensing procedures; and
  • Poor economic attractiveness of photovoltaics.

Solar development in Brazil

Below is a list of solar projects and activities that have been announced in Brazil:

Popular content

  • Ideal Institute (Institute for Development of Renewable Energies in Latin America), a non-governmental organization based in Florianopolis, southern Brazil, launched the Solar Label at the start of July. The Solar Label will be awarded to companies that have a minimum consumption of solar electricity. The company can either install its own system or purchased the energy on the free market.
  • In addition to ANEEL’s, a number of other small demonstration and pilot plant projects are said to be underway. pv magazine subscribers can read more here.
  • MPX and E.ON have built a one MW photovoltaic plant in Tauá. They are currently working on expanding it to two MW, and the two companies have received authorization to expand this to five MW. Overall they are aiming to increase the plant size to 50 MW.
  • Solaria is said to be working on a three MW photovoltaic plant, the details of which have not been disclosed.
  • Martifer Solar has signed an EPC contract with General Motors Brasil for the construction of a 300 kW photovoltaic installation in the state of Santa Catarina, Southern Brazil.
  • Yingli has partnered with Light ESCO, EDF Consultoria and the State of Rio de Janeiro to install photovoltaic modules at Brazilian football stadium, Estadio do Maracana in time for the 2014 FIFA World Cup.
  • Gehrlicher Ecoluz Solar do Brasil S.A. has grid connected a 408 kWp system at the Pituaçu stadium in Salvador de Bahia.
  • Cemig Geração e Transmissão SA has said it will undertake 5.6 MW worth of photovoltaic projects in Brazil over the course of 2012.

This content is protected by copyright and may not be reused. If you want to cooperate with us and would like to reuse some of our content, please contact: editors@pv-magazine.com.

Share

Related content

Elsewhere on pv magazine...

Leave a Reply

Please be mindful of our community standards.

Your email address will not be published. Required fields are marked *

By submitting this form you agree to pv magazine using your data for the purposes of publishing your comment.

Your personal data will only be disclosed or otherwise transmitted to third parties for the purposes of spam filtering or if this is necessary for technical maintenance of the website. Any other transfer to third parties will not take place unless this is justified on the basis of applicable data protection regulations or if pv magazine is legally obliged to do so.

You may revoke this consent at any time with effect for the future, in which case your personal data will be deleted immediately. Otherwise, your data will be deleted if pv magazine has processed your request or the purpose of data storage is fulfilled.

Further information on data privacy can be found in our Data Protection Policy.