Having put key PV projects into commercial operation, the company is capitalizing on their production. Scatec also has twice its current installed capacity under construction and nearly fourfold that amount – more than 4 GW – in the pipeline as 2018 expectations were surpassed.
The global market stagnated last year, with around 98 GW deployed. For 2019, the experts expect stronger solar growth, provided there are no setbacks in China.
The 540 MW project, in Brasileira, will feature 18 units with a capacity of 30 MW each. The developer is Brazil-based Gruppo Interalli and work on the giant plant is expected to start in the second quarter of the year.
Although power companies have urged the new administration of Jair Bolsonaro to reduce incentives for net metered solar distributed generation, ANEEL has proposed maintaining them until PV reaches a certain proportion of the electricity sector.
Two facilities were sold along with a 90 MW wind power plant generating the vendor around €700 million. Both solar projects were awarded 20-year PPAs in the most successful auction held by the Brazilian government, in August 2015.
The Brazilian module maker expects to start construction of a factory in the state of Tocantins in the second half of the year. The project is receiving support from the local ministry of environment.
According to figures from solar association ABSolar, most of the installed capacity – 371.9 MW – was installed in 2018. Commercial PV dominates with 43.2% as cheaper modules and higher electricity tariffs, combined with an extensive net metering regime, continue to fuel installation rates.
Including 80 MW of additional capacity at the testing stage, the country’s deployed PV capacity from large-scale solar auctions reached around 2.3 GW last year, according to a report by consultancy Greener. The study reveals a further 962 MW may be connected this year. Jinko, Canadian Solar and BYD are the largest module suppliers for the segment.
The 1 MW array – to be expanded to 5 MW – is being tested before official commissioning. The plant is at the Sobradinho dam, a 175 MW hydroelectric facility on the São Francisco River, in the state of Bahia.
The US$215 million Apodi solar park is located in the city of Quixeré, in the state of Ceará. The project was selected in Brazil’s second auction for renewables, which was held in 2015.
This website uses cookies to anonymously count visitor numbers. View our privacy policy.
The cookie settings on this website are set to "allow cookies" to give you the best browsing experience possible. If you continue to use this website without changing your cookie settings or you click "Accept" below then you are consenting to this.