Time for action

Germany has seen a sharp increase in solar grid-connection issues and many distribution network operators are reaching their limits. Regulators are yet to approve shared connections for solar and wind projects so planners must lay new lines and install transformers themselves.
Allowing batteries to provide various services to the grid has made Germany an attractive market for energy storage developers. | Photo: Kyon Energy

 PV Think Tank has reported that solar grid-connection requests rose 240% in 2023, a year that brought Germany around 15 GW of new solar. From 2026, the annual PV installation figure is expected to hit 22 GW.“Requests for grid connection are coming up against ever tighter operator capacities, partly because the current processes are inefficient, …

pv magazine
This article is part of pv+
Subscribe digitally to unlock exclusive investigative reporting, expert insights, in-depth analysis, and premium background coverage. Your subscription also includes full access to the digital edition of our magazine.