Mexico: Up to 40% of projects selected in auctions may not be built
Mexico Auctions: Santiago Barcón is a columnist for Energía Hoy and an advisor to Mexico’s Energy Regulatory Commission. Barcón explains that between 30 and 40% of projects assigned in Mexico’s first and second auctions may not actually be built. In addition, Barcón states that the Mexican electricity system is now more open to renewables, despite problems of transmission and bureaucracy. As a very positive aspect, Barcón highlights the enormous potential of distributed generation in the Latin American nation.
pv magazine: Mr. Barcón, how is the Mexican energy system changing?Santiago Barcón: It is a radical transformation after 75 years of state monopoly in which the Federal Electricity Commission (CFE) was basically the only player. There are now several players in the market, both in generation and in marketing and supply. What is strange is that …