Bangladesh’s upper court tells government to get serious about renewables

Responding to a petition seeking an order to protect vulnerable wildlife habitats, the High Court of Bangladesh has told policymakers in Dhaka to draw up a plan for 100% clean energy.
The International Renewable Energy Agency has estimated Bangladesh had 301 MW of grid-connected solar capacity at the end of 2020. | Graphic created by Max Hall, using content from freevectormaps.com, for pv magazine

The High Court of Bangladesh has responded to a petition seeking to protect the country’s wetland habitats by calling on the government to prepare a masterplan to make the nation 100% powered by renewables.

Citing the example set by Germany in raising the proportion of renewable energy generation in its national power mix, the court said Dhaka should formulate a renewable energy act and establish a renewables ministry and a renewable energy commission, to expedite clean power generation.

The court issued the directives as it responded to a writ petition filed by the Bangladesh Environment Lawyers Association (BELA) which successfully sought an order to save Bangladeshi wetlands.

AgriPV

Solar PV could disrupt the fossil fuel industry and help with two of the biggest sustainability challenges of our times: biodiversity loss and food production. pv magazine’s UP initiative has this year shone a spotlight on agrivoltaics. Read our coverage here.

“Presently … fossil fuel is considered as very harmful for climate,” said the high court in its verdict on the BELA petition. “The developed world has stopped using fossil fuel [sic] and engaged in generation of renewable energy as an alternative.”

The Bangladeshi renewables industry applauded the court’s observation and said clean power lacked impetus because it had not received enough promotion by the government.

Responsibility for clean power deployment currently sits with Bangladesh’s Ministry of Energy and Mineral Resources, which still overwhelmingly focuses on conventional, fossil fuel power generation, according to renewables-industry professionals.

“We have long been demanding to establish a separate ministry to promote [the] renewable energy sector,” said Dipal C Barua, president of the Bangladesh Solar and Renewable Energy Association, in response to one of the points raised by the court, and he added, the Sustainable and Renewable Energy Development Authority wing of the power ministry was not sufficient to drive the nation’s energy transition.

Barua lauded a recent government decision to remove permission for ten coal-fired power plants and welcomed an ambition, announced by the power minister, for the country to generate 40% of its electricity from renewables by 2041.

Vulnerable

The issue has gained added attention as Bangladeshi is currently chairing the Climate Vulnerable Forum of 48 nations disproportionately affected by global heating.

Bangladesh’s current five-year-plan – its eighth, which started this year – has also pledged aggressive funding and policy support for renewables.

At present, around 3% of Bangladesh’s energy generation capacity is accounted for by its 766.49 MW of clean energy project capacity.

This content is protected by copyright and may not be reused. If you want to cooperate with us and would like to reuse some of our content, please contact: [email protected].

Written by

Comments

High court directs government to pay attention to renewable energy – BizData Insight
Dec 06, 2022

[…] pv magazine […]

Mohammad Helal Uddin
Jul 22, 2021

We tried to convince the government at least to have RE Act in lieu of RE policy 2008 with a view to speedy implementation RE Targets primarily by the SoE electrical companies, compliance of standard RE panels and inverter in near past (2017-2020). SREDA drafted the would be RE Act with the consultation of experts of home and overseas. A few seminars were arranged.
I still hope RE Act will be there tomorrow. SREDA may be converted and with a bigger size into RE ministry.

Bangladesh’s upper court tells government to get serious about renewables - Global Bangla Television
Jul 20, 2021

[…] This content is protected by copyright and may not be reused. If you want to cooperate with us and would like to reuse some of our content, please contact: [email protected]. […]