Together with the installer and aleo-partner Ailita Engineering S.r.l. as well as the
Bank BIIS – Banca Infrastrutture Innovazione e Sviluppo we founded a special
purpose vehicle in order to offer both a technical and a financial solution, explained
Giovanni Buogo, Sales Manager Europe at aleo solar AG.
Vittorio Venetos Mayor, Mr Gianantonio Da Re states: For us as a public institution, secure financing and a cooperation with reliable partners were in the forefront of the tendering process and the project: aleo solar and its partners provided quality both in terms of products, as well as service in the different phases of the project.
The solar park has been feeding green electricity into the public grid since May
2011. aleo partner Ailita Engineering S.r.l. ensured the professional installation of
the modules and construction took less than two months. The plant is expected to
generate an annual yield of 1,200,000 to 1,250,000 kilowatt hours.