Q.Cells completes 91 MW PV park financing

Share

Overall, the German company says the Brandenburg-Briest project, co-developed with Module 24, took a total of eight weeks to construct (work began last November and was finished before the end of the year). Following the final financial installment from an unnamed bank, the commercial part of the project has also now been completed.

Overall, the project is comprised of three systems, which are expected to generate enough electricity for over 22,500 households. The first two – Brandenburg-Briest West and Brandenburg-Briest East – are worth a total of 60 MWp. Ownership was transferred to Hamburg asset management company, Luxcara last November. The final system, owned by Berlin-based MCG Management Capital Group, is worth 31 MWp.

"Q.Cells sets benchmarks when it comes to constructing large-scale plants, for example by deploying the megawatt-block standard that we had developed," commented Frank Danielzik, director systems and operations Germany.

"We are very pleased by this lighthouse project to have demonstrated our experience and outstanding competence in the systems business," added Clemens Jargon, head of marketing, sales and product management.

Q-Cells has also been involved in a number of other larger solar projects in Germany this year, including the 82 MW Finsterwalde project, the 46 MWp Zerbst system and the 21 MWp solar park in Ammerland.

Popular content

This content is protected by copyright and may not be reused. If you want to cooperate with us and would like to reuse some of our content, please contact: editors@pv-magazine.com.

Share

Related content

Elsewhere on pv magazine...

Leave a Reply

Please be mindful of our community standards.

Your email address will not be published. Required fields are marked *

By submitting this form you agree to pv magazine using your data for the purposes of publishing your comment.

Your personal data will only be disclosed or otherwise transmitted to third parties for the purposes of spam filtering or if this is necessary for technical maintenance of the website. Any other transfer to third parties will not take place unless this is justified on the basis of applicable data protection regulations or if pv magazine is legally obliged to do so.

You may revoke this consent at any time with effect for the future, in which case your personal data will be deleted immediately. Otherwise, your data will be deleted if pv magazine has processed your request or the purpose of data storage is fulfilled.

Further information on data privacy can be found in our Data Protection Policy.