Total French PV capacity over 1 GW

Share

French 2010 installations were more than double those of 2009, and there are now 152,000 PV systems installed in both the country and its territories.

France now has the seventh-largest installed PV capacity in the world, after Germany, Spain, Japan, Italy, the U.S., and the Czech Republic. The Ministry expects that between one GW and 1.5 GW of new PV will be installed in 2011 and 2012.

Though the government didn't release the number of central-station, ground-mounted projects, the vast majority of French solar installations are in distributed applications. There were 13,000 projects greater than three kilowatts (kW), representing 70 percent of total capacity installed in 2010. Only 92 projects installed in 2010 were greater than 250 kW, for a total of 128 MW.

Several ground-mounted projects in the pipeline will be installed in the next several months, and some of the projects that were under development before the government's moratorium will proceed under the previous policy.

New regulations

As already reported, as a means to limit costs to ratepayers, France’s Ministry has set a new target of 500 MW per year for the installation of PV. In comparison, Germany, one of France's main trading partners, has recently reaffirmed its target of 3.5 GW per year.

The French Ministry's proposal cuts PV tariffs by 20 percent and will severely limit new applications for any rooftop project greater than 100 kW and all ground-mounted projects.

To restrict the type and number of installations, all rooftop projects greater than 100 kW, but less than 250 kW, will have to respond to a "simplified" Request for Proposal (RFP) or "call for tender" as it is known in Europe. Winners of the RFP will be chosen on several non-price factors and will receive the fixed tariffs.

However, all rooftop projects greater than 250 kW, and ground-mounted projects of any size will have to respond to a more conventional RFP. Winners will be based on price, environmental impact, innovation, and other factors. Thus, PV projects greater than 250 kW will be effectively removed from the French feed-in tariff program.

The use of RFPs reflect the famed French penchant for centralized control and administration, preferred by French Governments since Louis XIV (the "Sun King") concentrated power in the hands of the Versailles nobility.

The new proposal gives the Ministry all decision-making authority regarding who will and will not install PV greater than 250 kW. Critics suggest that this is not only a way to rein in the rapid growth of solar, but also a recipe for favoring preferred contractors.

As recently as early 2010, the Ministry raised tariffs for PV, as well as for geothermal, and biomass. At the time, solar advocates warned the French Government, to no avail, that they were in danger of overheating the French PV market at the expense of the entire renewable energy program. See 2010 French Tariffs Raise Price for Solar, Geothermal, and Biomass.

Over cost due to fossil fuels, not renewables

With the rapid growth of PV in France, there have been accusations that renewables have created a huge debt in un-funded utility charges.

France collects a public goods charge, the Contribution au Service Public de l'Électricité (CSPE), from electricity consumers in order to pay for renewable energy, fossil-fired combined heat and power, and for the bills of consumers who can't pay them themselves.

In an unusual twist on the concept of public goods charge, the CSPE also pays the over cost that can't be recovered in rates of generating electricity from fossil fuels in French overseas territories. Consumers in French overseas territories pay the same electricity rates as Parisians, even though the cost of generating electricity is far higher than in continental France.

Electricité de France (EDF), the partially privatized utility serving France and its territories, has for several years not been collecting sufficient funds to cover the cost of the CSPE.

From 2007 through 2010, EDF had run up a debt of €2.8 billion. The cost of renewables represents only 10 percent to 15 percent of the total unfunded debt. The cost of fossil fuels accounted for 70 percent to nearly 90 percent of the debt, says the Comité de Liaison Energie Renouvelables (CLER). This is the same time period when oil prices reached their zenith, before crashing along with the global economy.

The situation with the CSPE in France is not dissimilar to that in Spain, where the over costs of fossil-fuel fired generation during the run-up in oil prices in 2007 and 2008 were attributed to the costs of renewable energy.

Critics note that despite wind energy's steady growth of one GW per year, it is insufficient to meet France's renewable energy targets. The new limits on PV – one-seventh the annual target of Germany – will only exacerbate the problem.

Nevertheless, the French Government's action illustrates the flexibility of feed-in tariffs as a policy tool by raising the tariffs for the technologies they want, while lowering those of the technologies they fear.

This content is protected by copyright and may not be reused. If you want to cooperate with us and would like to reuse some of our content, please contact: editors@pv-magazine.com.

Popular content

U.S. startup offers meter socket adapter that simplifies solar, battery, EV charging connection

04 December 2024 ConnectDER has secured $35 million in Series D funding to support its meter socket adapter (MSA) business, which integrates solar, storage, EV chargin...

Share

Leave a Reply

Please be mindful of our community standards.

Your email address will not be published. Required fields are marked *

By submitting this form you agree to pv magazine using your data for the purposes of publishing your comment.

Your personal data will only be disclosed or otherwise transmitted to third parties for the purposes of spam filtering or if this is necessary for technical maintenance of the website. Any other transfer to third parties will not take place unless this is justified on the basis of applicable data protection regulations or if pv magazine is legally obliged to do so.

You may revoke this consent at any time with effect for the future, in which case your personal data will be deleted immediately. Otherwise, your data will be deleted if pv magazine has processed your request or the purpose of data storage is fulfilled.

Further information on data privacy can be found in our Data Protection Policy.