Poland lowers PV support before law comes into force

Share

According to Polish law firm DMS DeBenedetti Majewski Szcze?niak, while the draft RES Act has been finalized, a number of changes have been announced in an introductory law, not yet made public. This third draft has been sent to the country’s Council of Ministers, which is expected to review it by this Wednesday.

Under the changes, says DMS DeBenedetti Majewski Szcze?niak, the photovoltaic correction coefficients for green certificates (GCs) have been lowered. Furthermore, instead of being presented in the RES Act, they will appear in the law implementing the "three-pack" – the RES Act, the Gas Law and the Energy Law.

Originally, all photovoltaic installations were set to receive a correction coefficient of 2.85 for each GC between 2013 and 2014. This would have installations, regardless of size or location, earn around €0.24/kWh.

However, under the changes, rooftop installations between 100 kW and 1 MW will receive a correction coefficient of 2.85, while other installations between 100 kW and 1 MW will receive 2.75, and all installations between 1 and 10 MW will receive just 2.45. As before, these correction coefficients will degress on an annual basis until 2017, by 5.5%.

Commenting, lawyer Christian Schnell tells pv magazine that while the rates have been lowered, his clients are still satisfied. "21 Eurocent for 1MW to 10MW is still a very good tariff compared to 13.5 Eurocent in Germany," he said.

For installations above 10 MW, the situation is not so clear. "Right now it has to be checked how larger investments consisting of a few 10 MW installations have to be structured – that’s lawyers work," he said, adding that on a positive note, "The new law still allows for merchant trading, although in a limited way. With this combined-floor PPAs and CPAs are still possible, and project finance will increase substantially, as the new law gives stability."

It has been further announced that the feed-in tariff will be officially introduced in a by-law to the RES Act. The rates are expected to be as follows:

  • Rooftop installations up to 10 kW – PLN 1.30/kWh (around €0.32; US$0.41)
  • Other installations up to 10 kW – PLN 1.15/kWh
  • Rooftop 10kW to 100 kW – PLN 1.15/kWh
  • Other installations 10 kW to 100 kW – PLN 1.10/kWh

A number of other changes have been made, including: an obligation by industrial consumers and stock exchange members to purchase GCs; a "softening" of the headroom solution — devised to avoid an oversupply of GCs — whereby the Ministry may increase the percentage obligation to purchase green energy to an appropriate value, but is not obliged to do so; and the inclusion of energy storage facilities in the RES Act if they are connected to the renewable energy installation.

The Polish government is still said to be confident that the three pack will enter into law at the start of next year, although the laws are yet to be tabled in parliament, and filed with the European Commission for notification. A process, Schnell says, which can take up to 6 months.

Popular content

Industry is also skeptical that the RES Act will be introduced in January. Indeed, CEO of Polish company Easy Solar, Marcin Dolata believes the law may only come into force at the end of 2013.

For more detailed information on the Polish photovoltaics market, see the October edition of pv magazine. Solarpraxis AG will also be holding a workshop (in German) on November 6 in Berlin, "Photovoltaik in Polen". Find more information here.

This content is protected by copyright and may not be reused. If you want to cooperate with us and would like to reuse some of our content, please contact: editors@pv-magazine.com.

Share

Related content

Elsewhere on pv magazine...

Leave a Reply

Please be mindful of our community standards.

Your email address will not be published. Required fields are marked *

By submitting this form you agree to pv magazine using your data for the purposes of publishing your comment.

Your personal data will only be disclosed or otherwise transmitted to third parties for the purposes of spam filtering or if this is necessary for technical maintenance of the website. Any other transfer to third parties will not take place unless this is justified on the basis of applicable data protection regulations or if pv magazine is legally obliged to do so.

You may revoke this consent at any time with effect for the future, in which case your personal data will be deleted immediately. Otherwise, your data will be deleted if pv magazine has processed your request or the purpose of data storage is fulfilled.

Further information on data privacy can be found in our Data Protection Policy.