Abengoa beats fossil fuels on price with solar PV & CSP plus storage in Chile

Share

Abengoa was awarded contracts to supply 950 gigawatt-hours (GWh) of electricity annually to Chile's Central Grid (SIC) in an auction held last week. To deliver this energy, the company has announced that it will build two 110 MW solar power tower CSP plants, as well as a 100 MW solar PV project.

The two projects will employ a thermal energy storage system developed by Abengoa, which the company says will allow it to deliver electricity 24 hours a day. Unlike the other electricity supply contracts for solar PV, which were awarded for eight hour blocks in the auction, Abengoa was awarded contracts for 24-hour electricity supply.

The company will be supplying this round-the-clock electricity for the sum of US$0.115 per kilowatt-hour (KWh), which is a very low cost for combined solar and storage, particularly for CSP. Since this supply auction was open to conventional generators as well as renewable energy sources, it appears that Abengoa's solar and storage solution beat other bids by fossil fuel generators on price.

“Abengoa seeks to be an important actor in the electricity generation market in Chile, providing clean and competitive energy at the same price and characteristics as traditional energy generators,” Abengoa CEO Manuel Sánchez Ortega declared in a press statement.

Popular content

GTM Research Solar Analyst Adam James notes that the extremely strong irradiation in Northern Chile as well as the lower cost of capital from Abengoa's yieldco are likely contributing factors to this very low price. He also notes that the company may benefit from additional electricity sales beyond what it is contracted to deliver.

The contracts were awarded in block 4 of the supply auction, under which Abengoa is contracted to supply electricity from January 2019 through the end of 2033. In the same auction SunEdison was awarded electricity supply contracts for which it will build 350 MW of solar PV.

Update: This article was updated from its original version with analysis from GTM Research at 13:00 EST.

This content is protected by copyright and may not be reused. If you want to cooperate with us and would like to reuse some of our content, please contact: editors@pv-magazine.com.

Share

Related content

Elsewhere on pv magazine...

Leave a Reply

Please be mindful of our community standards.

Your email address will not be published. Required fields are marked *

By submitting this form you agree to pv magazine using your data for the purposes of publishing your comment.

Your personal data will only be disclosed or otherwise transmitted to third parties for the purposes of spam filtering or if this is necessary for technical maintenance of the website. Any other transfer to third parties will not take place unless this is justified on the basis of applicable data protection regulations or if pv magazine is legally obliged to do so.

You may revoke this consent at any time with effect for the future, in which case your personal data will be deleted immediately. Otherwise, your data will be deleted if pv magazine has processed your request or the purpose of data storage is fulfilled.

Further information on data privacy can be found in our Data Protection Policy.