Brazil has passed the historic mark of 7 GW of operational PV power, according to Associação Brasileira de Energia Solar Fotovoltaica (ABSolar).
Since 2012, investors have dumped more than BRL 35 billion ($6.8 billion) into the country's solar sector. The large-scale PV segment has reached 3 GW –equivalent to 1.6% of the electricity mix. In 2019, solar was the most competitive renewable energy source in auctions A-4 and A-6, with average prices below $21/MWh.
In the distributed-generation PV segment, total installed PV capacity has passed 4 GW, with more than BRL 20 billion of investment. Residential consumers account for 72.8% of all systems installed.
The Ministry of Mines and Energy and the state-run Empresa de Pesquisa Energetica (EPE) agency recently presented the National Energy Plan (PNE) up to 2050. The Brazilian government has set a renewable energy target of around 45% by 2030 under the new strategy.
The PNE also defines the most important challenges that PV technology will face over the coming decade. Greater variability and less predictability in generation will be the main issue for the integration of solar PV into the energy mix over the short term.
“We need to improve price models for electricity, as well as the planning and operation of the electrical system, so it represents the characteristics and uncertainties inherent to each primary source,” the energy ministry said, arguing that this will ensure greater operational security and predictability over the medium term.
This content is protected by copyright and may not be reused. If you want to cooperate with us and would like to reuse some of our content, please contact: editors@pv-magazine.com.
5 comments
By submitting this form you agree to pv magazine using your data for the purposes of publishing your comment.
Your personal data will only be disclosed or otherwise transmitted to third parties for the purposes of spam filtering or if this is necessary for technical maintenance of the website. Any other transfer to third parties will not take place unless this is justified on the basis of applicable data protection regulations or if pv magazine is legally obliged to do so.
You may revoke this consent at any time with effect for the future, in which case your personal data will be deleted immediately. Otherwise, your data will be deleted if pv magazine has processed your request or the purpose of data storage is fulfilled.
Further information on data privacy can be found in our Data Protection Policy.