Electrification could drive 51 GW of solar in Canada by 2050

And that figure is based on a less ambitious climate change policy than the one Ottawa has committed to since the North American Renewable Integration Study started, in 2018.
With the NARIS study working from a baseline 2 GW of grid connected solar in Canada, the nation had already hit almost 3.33 GW by the end of 2020, according to the International Renewable Energy Agency. | Graphic created by Max Hall, using content from freevectormaps.com, for pv magazine

A modeling exercise carried out to determine the best path to a low carbon energy system across North America has estimated 34 GW of solar could be required in Canada by mid-century, rising to 51 GW with extensive electrification of heating and transport.

Industry body the Canadian Renewable Energy Association (CanREA) has welcomed the findings of the North American Renewable Integration Study (NARIS), and pointed out the government has raised its climate change ambition since the modeling exercise was started, three years ago.

With the NARIS study – carried out by Natural Resources Canada, the United States Department of Energy and the Secretaría de Energía de México – having made its solar prediction based on an 80% reduction in carbon emissions across the three nations’ energy systems by mid century, CanREA has pointed out Ottawa and the U.S. have since pledged to attain net zero economies by 2050, with Canada aiming to eliminate carbon from its energy system by that point and the U.S. promising to do so by 2035.

The NARIS findings modeled by the U.S. National Renewable Energy Laboratory predicted the route to an 80% carbon free energy system in Canada would require 7-32 GW of rooftop solar, depending on the scenario mapped in an exercise which examined four broad outcomes plus 38 variations.

The Canadian industry body, which welcomed the findings of the study on its website yesterday, used the occasion to call on the federal government to ramp up the roll-out of solar and wind generation capacity and improve electricity network links between the nation’s provinces.

This content is protected by copyright and may not be reused. If you want to cooperate with us and would like to reuse some of our content, please contact: [email protected].

Written by

Comments

Ontario confirms 1.5 GW-plus tender for battery storage – pv magazine USA
Oct 14, 2022

[…] is building the electricity generation and storage needed to support our success in driving electrification and attracting new jobs to the province, including unprecedented investments from electric […]

A net-zero Canada would need 1.6 GW of solar per year from now on – Solar Life
Nov 25, 2021

[…] industry body for renewable energy businesses in Canada has called upon federal and provincial politicians to take the actions required to drive 1.6 GW of […]

Randy Wester
Jul 01, 2021

Canadian solar for heating?

It could work, especially if the panels are in southern Arizona.

The supply of winter’s daily solar electricity is going to be brief and weak.

Show replies
Hide replies
Jeff
Jul 02, 2021

Extreme insulation will go a long ways mixed with heat pumps that get a 4 to 1 ratio of energy.. With the heat wave in British Columbia the heat pumps would be cooling their homes saving lives.