890 MW of solar PV clears in Brazil's reserve auction

Share

On Friday, Brazil's National Electric Energy Agency (ANEEL) and Electricity Trading Chamber (CCEE) held an auction for reserve electric capacity, which included a portion limited to solar projects.

This is the first federal auction specifically for solar, following on a solar-only auction in the state of Pernambuco at the end of 2013. 31 solar PV projects totaling 890 MW which cleared the federal auction will be awarded 20-year power purchase agreements at an average price of US$0.087/kWh.

Developers have until October 2017 to begin supplying power. GTM Research Solar Analyst Adam James told pv magazine that while he believes that prices are too low for projects to be built today, a lot can change in three years.

“Given the current taxes on PV equipment, those levels are too low,” James explained. “And how high prices are on the spot market, it also seems unnecessary for prices to be that low.”

A major factor in project economics is the cost of capital, and Brazilian development bank BNDES has made available low-cost financing for PV projects which utilize local modules.

Popular content

And while there is currently little PV manufacturing capacity available to meet this need, James estimates that there have been four or five announcements of PV module factories planned for Brazil.

James cautions casual observers from assuming that all of these projects will come to fruition, and he expects that even with three years some of the 31 will not make it. “There is just a lot of uncertainty here,” observed James. “This is the first step in a long process.”

Many of the projects are planned for the state of Bahia, however official statements were unclear as to exact capacities and locations.

This content is protected by copyright and may not be reused. If you want to cooperate with us and would like to reuse some of our content, please contact: editors@pv-magazine.com.

Share

Related content

Elsewhere on pv magazine...

Leave a Reply

Please be mindful of our community standards.

Your email address will not be published. Required fields are marked *

By submitting this form you agree to pv magazine using your data for the purposes of publishing your comment.

Your personal data will only be disclosed or otherwise transmitted to third parties for the purposes of spam filtering or if this is necessary for technical maintenance of the website. Any other transfer to third parties will not take place unless this is justified on the basis of applicable data protection regulations or if pv magazine is legally obliged to do so.

You may revoke this consent at any time with effect for the future, in which case your personal data will be deleted immediately. Otherwise, your data will be deleted if pv magazine has processed your request or the purpose of data storage is fulfilled.

Further information on data privacy can be found in our Data Protection Policy.