Trial operation of the first generating unit of Iraq’s 1 GW Basra solar power plant is underway.
An update from the Iraqi Ministry of Electricity explains 61 MW from the first of four 250 MW units has begun operating. It adds that loads will be increased sequentially until the first unit reaches its full 250 MW capacity, at which point the plant will be connected to the national grid via the New Rumaila and Suq al-Shuyukh transmission lines.
The power plant is set to cover an area of approximately 9,000 dunams (900 hectares) in the southeastern governorate of Basra once it reaches its full capacity. Full commissioning is expected by 2028.
The project broke ground last July. It is being built by France’s TotalEnergies, which holds a 45% stake in the project. Basrah Oil Co. holds 30% and QatarEnergy holds the remaining 25%.
According to details on TotalEnergies’ website, the plant is being divided into four units to adapt more easily to the capacity of the local grid. The developer adds that the project will supply electricity to 350,000 homes in the region and will contribute to the Iraqi government's goal of meeting 12% of its energy needs from renewable sources by 2027.
Iraq aims to deploy 12 GW of solar power by the end of the decade. According to the International Renewable Energy Agency (IRENA), the country had 42 MW of solar by the end of 2024.
The Basra plant is Iraq’s first gigawatt-sized project under construction. In September, the first phase of a 300 MW solar site in the Karbala governorate of central Iraq entered operations. Last June, US-based developer UGT Renewables signed a contract with the Iraqi government to build a 3 GW solar project.
Iraq's customs authority recently reduced customs duties on solar systems from 33% to 5% in a bid to encourage greater solar uptake.
This content is protected by copyright and may not be reused. If you want to cooperate with us and would like to reuse some of our content, please contact: editors@pv-magazine.com.

By submitting this form you agree to pv magazine using your data for the purposes of publishing your comment.
Your personal data will only be disclosed or otherwise transmitted to third parties for the purposes of spam filtering or if this is necessary for technical maintenance of the website. Any other transfer to third parties will not take place unless this is justified on the basis of applicable data protection regulations or if pv magazine is legally obliged to do so.
You may revoke this consent at any time with effect for the future, in which case your personal data will be deleted immediately. Otherwise, your data will be deleted if pv magazine has processed your request or the purpose of data storage is fulfilled.
Further information on data privacy can be found in our Data Protection Policy.