The Central Electricity Board (CEB) of Mauritius has opened a tender for grid-tied, roof-mounted hybrid solar systems.
According to available tender details, the solar systems will have a cumulative capacity of 2 MW and be deployed on the island of Rodrigues, east of the main island of Mauritius. The chosen developer will be responsible for the supply, installation, testing and commissioning of the solar system.
The accompanying bidding document adds an optional lot covering the supply, installation, testing and commissioning of modular battery energy storage systems (BESS), up to a total 1 MWh of cumulative capacity.
The project shall be carried out on a turnkey basis, with the solar installations deployed on various public buildings with capacities ranging between 5 kW and 50 kW.
The work will be financed by a grant from the Green Climate Fund, alongside additional investment from the government of Mauritius. Interested applicants must submit their bids electronically by Feb. 2, 2026.
Mauritius currently has 168.5 MW of operational solar, according to the Africa Solar Industry Association’s (AFSIA) project database.
In November, CEB warned against a growing number of unauthorized solar systems in Mauritius, advising those not registered by Jan. 15, 2026, risk facing disconnection.
This content is protected by copyright and may not be reused. If you want to cooperate with us and would like to reuse some of our content, please contact: editors@pv-magazine.com.

By submitting this form you agree to pv magazine using your data for the purposes of publishing your comment.
Your personal data will only be disclosed or otherwise transmitted to third parties for the purposes of spam filtering or if this is necessary for technical maintenance of the website. Any other transfer to third parties will not take place unless this is justified on the basis of applicable data protection regulations or if pv magazine is legally obliged to do so.
You may revoke this consent at any time with effect for the future, in which case your personal data will be deleted immediately. Otherwise, your data will be deleted if pv magazine has processed your request or the purpose of data storage is fulfilled.
Further information on data privacy can be found in our Data Protection Policy.