From pv magazine Spain
Spain's Ministry for Ecological Transition and the Demographic Challenge (MITECO) has launched its first tender to allocate grid capacity at eight electricity transmission nodes in Andalusia, Aragon, Castilla-La Mancha, Catalonia, Galicia, and the Basque Country.
The total access capacity amounts to 3,681 MW and corresponds to nodes where major industrial developments have submitted requests.
These grid points are oversubscribed with applications from large consumers. Until now, each request was evaluated individually. Due to overloads at some nodes, a competitive process has been introduced. When grid operator Red Eléctrica de España (REE) receives a demand access request for a specific node, it publishes it on its website.
If additional requests are submitted within one month and available capacity is insufficient, the node is assigned to a tender among all interested parties who expressed interest during that period.
Applicants have one month to submit the required documentation. After review, which may include a report from REE, MITECO will resolve each tender within six months of the call. Developers must submit financial guarantees based on three criteria, amounting to €25/kW for each criterion. These guarantees will be returned once compliance is verified.
This is the first time demand access is allocated through a regulated tender using three evaluation criteria. The process marks a shift, giving preference to projects that reduce CO₂ emissions, such as electrifying industrial processes. After this initial criterion, projects will be scored based on investment size and expected commissioning timelines. The criteria include:
-
Emissions reduction (decarbonization impact)
-
Planned investment volume
-
Timeline for consumption start-up
The eligible nodes and available capacity are:
-
Arrigorriaga (Bizkaia) 400 kV – 993 MW
-
Brazatortas (Ciudad Real) 400 kV – 1,217 MW
-
Cristóbal Colón (Huelva) 220 kV – 503 MW
-
Francolí (Tarragona) 220 kV – 216 MW
-
Mercedes Benz (Vitoria) 220 kV – 387 MW
-
New Vigo 220 kV – 182 MW
-
Palos (Huelva) 220 kV – 277 MW
-
Terrer (Zaragoza) 400 kV – 410 MW
This content is protected by copyright and may not be reused. If you want to cooperate with us and would like to reuse some of our content, please contact: editors@pv-magazine.com.

By submitting this form you agree to pv magazine using your data for the purposes of publishing your comment.
Your personal data will only be disclosed or otherwise transmitted to third parties for the purposes of spam filtering or if this is necessary for technical maintenance of the website. Any other transfer to third parties will not take place unless this is justified on the basis of applicable data protection regulations or if pv magazine is legally obliged to do so.
You may revoke this consent at any time with effect for the future, in which case your personal data will be deleted immediately. Otherwise, your data will be deleted if pv magazine has processed your request or the purpose of data storage is fulfilled.
Further information on data privacy can be found in our Data Protection Policy.