A further 1 GW of solar is operational at the Mohammed bin Rashid Al Maktoum Solar Park, the world’s largest single-site solar park, located in the United Arab Emirates.
Work is currently underway on the sixth phase of the project that will add a total of 1.8 GW of solar to the site, which is being implemented by Dubai Electricity and Water Authority (DEWA) under an independent power producer (IPP) model.
An update published by the government of Dubai confirms the sixth phase is approximately 68.59% complete, having reached the 1 GW threshold, with the remaining 800 MW under construction.
Over 2.2 million solar panels have been installed to date, with the number on track to reach over 3.9 million by the time the current phase of work is completed next year.
To date, the solar park’s cumulative production capacity stands at over 3.8 GW, according to figures published by DEWA. By the end of the decade, its capacity is expected to reach over 7.2 GW, exceeding the original 5 GW target, and will contribute to around 34% of Dubai’s total electricity capacity.
In February, DEWA issued a call for developers to assist with the seventh phase of the project on an IPP basis. The tendered solar facility will have a capacity ranging between 1.6 GW and 2 GW and will be connected to 1 GW of battery capacity, making it one of the largest solar-plus-storage projects in the world.
In April, DEWA Managing Director and CEO Saeed Mohammed Al Tayer announced that 47 global companies had expressed interest in developing the next phase.
This content is protected by copyright and may not be reused. If you want to cooperate with us and would like to reuse some of our content, please contact: editors@pv-magazine.com.

By submitting this form you agree to pv magazine using your data for the purposes of publishing your comment.
Your personal data will only be disclosed or otherwise transmitted to third parties for the purposes of spam filtering or if this is necessary for technical maintenance of the website. Any other transfer to third parties will not take place unless this is justified on the basis of applicable data protection regulations or if pv magazine is legally obliged to do so.
You may revoke this consent at any time with effect for the future, in which case your personal data will be deleted immediately. Otherwise, your data will be deleted if pv magazine has processed your request or the purpose of data storage is fulfilled.
Further information on data privacy can be found in our Data Protection Policy.