RWE Renewables has withdrawn its proposed 99.9 MW Butterfly (Glöyn Byw) solar‑plus‑storage project in Wrexham, Wales, after concluding that grid connection availability made the scheme unviable at this stage.
“After careful consideration and a detailed review of grid connection availability and overall project viability, we have decided not to proceed with plans for the proposed Butterfly/Glöyn Byw solar farm at this time,” the company said in an emailed statement.
The project was planned across three parcels of agricultural land south of Wrexham, with underground cabling to the Legacy National Grid substation. RWE had identified grid access as a key design challenge from the outset, with two alternative connection routes still under assessment as recently as September 2025.
RWE’s withdrawal comes as Great Britain’s grid connection queue remains severely congested, with NESO and Ofgem pushing reforms after a 460% surge in applications between January and June 2025 and delays stretching to as much as 15 years. The cancellation underscores that grid constraints are no longer only a transmission‑level bottleneck; they are now shaping early‑stage project design and viability decisions for solar‑plus‑storage developers across the UK.
The company stressed that solar and co‑located storage remain central to its UK strategy. “RWE remains committed to investing in renewable energy in the UK and bringing forward projects that can be delivered efficiently and contribute to both local and national energy needs,” it said.
The Wrexham decision lands amid wider concerns about the pace of grid investment. A new report by the EU Agency for the Cooperation of Energy Regulators (ACER) found that almost two‑thirds of EU distribution system operators are exempt from preparing network development plans, and that fragmented planning obligations continue to undermine the efficiency of rising grid investment in Europe.
RWE expanded its global PV portfolio to 7.01 GW in 2025 in 2025 and plans €35 billion in investments by 2030, including 6 GW of new flexible capacity and storage in Germany. The company’s latest results reinforce that the Wrexham cancellation reflects grid constraints rather than any strategic shift away from solar or co‑located storage.
This content is protected by copyright and may not be reused. If you want to cooperate with us and would like to reuse some of our content, please contact: editors@pv-magazine.com.

By submitting this form you agree to pv magazine using your data for the purposes of publishing your comment.
Your personal data will only be disclosed or otherwise transmitted to third parties for the purposes of spam filtering or if this is necessary for technical maintenance of the website. Any other transfer to third parties will not take place unless this is justified on the basis of applicable data protection regulations or if pv magazine is legally obliged to do so.
You may revoke this consent at any time with effect for the future, in which case your personal data will be deleted immediately. Otherwise, your data will be deleted if pv magazine has processed your request or the purpose of data storage is fulfilled.
Further information on data privacy can be found in our Data Protection Policy.