A disturbance in Estonia’s power system on Jan. 20 forced both EstLink interconnections between Estonia and Finland offline, cutting roughly 1,000 MW of capacity, equivalent to about 20% of the Baltic region’s winter electricity load.
The shortfall was initially covered by support from the continental European grid, as the 500 MW AC connection between Poland and Lithuania operated at double its rated capacity to compensate. Later, reserve capacity within the Baltic states was deployed.
The oscillations were triggered by a 100 MW/200 MWh battery energy storage system in Kiisa, just south of Tallinn, one of the largest battery storage systems in the Baltics. The incident occurred during final grid connection testing, which caused the DC cables to trip.
The €100 million facility, developed by Estonian company Evecon in partnership with French firms Corsica Sole and Mirova, features 54 battery containers supplied by Nidec Conversion.
To continue reading, please visit our ESS News website.
This content is protected by copyright and may not be reused. If you want to cooperate with us and would like to reuse some of our content, please contact: editors@pv-magazine.com.

By submitting this form you agree to pv magazine using your data for the purposes of publishing your comment.
Your personal data will only be disclosed or otherwise transmitted to third parties for the purposes of spam filtering or if this is necessary for technical maintenance of the website. Any other transfer to third parties will not take place unless this is justified on the basis of applicable data protection regulations or if pv magazine is legally obliged to do so.
You may revoke this consent at any time with effect for the future, in which case your personal data will be deleted immediately. Otherwise, your data will be deleted if pv magazine has processed your request or the purpose of data storage is fulfilled.
Further information on data privacy can be found in our Data Protection Policy.